Day 1 of pool construction.   Now waiting for county inspector.
April 26th, 2017
Day 2 of pool construction.   Concrete poured.
May 4th, 2017
Day 5 of pool construction.   Plumbed and prepared for Deck Concrete pour.
May 8th, 2017
Day 6 of pool construction.   Deck Concrete poured.  The rear and sides of the lanai will be removed and the entire area will be screened in.  Also, will have solar panels on the roof of the house.  Still ahead of schedule.
May 9th, 2017
Day 7 of pool construction.   They got a lot done. Now we wait for the enclosure folks to put up the screens and tear up the lanai. Also, the electrician has to do all the wiring. The solar panel folks have to install the solar system on the roof. And after all that is done, the pool folks come back to spray in the final finish in the pool and paint the cool deck. We are very close to being done if the contractors mentioned above get here in a timely fashion.
Do I need a new swim suit? No, I think I'm good for now.
May 17th, 2017
Day whatever (lost count) of pool construction.   We've had a work stoppage waiting for the screen people.  They came out today and tore out the walls in the lanai.  They will be back, hopefully, on Monday, the 22nd to do the screen.  We still may be on track to finish late next week.  The pool folks will be back right after the screen folks to finish up in 1 or 2 days.  Then we will fill the pool.  The solar folks will be here Thursday, the 25th to install the panels.  They will finish on Friday.  Also, the landscaper will be here on the same Thursday and Friday to do their thing.  So, with luck, we will be completed by Friday, the 26th of May.  And that is about a week ahead of the original schedule.  I'm ready.  I've blown up my water wings.